CD7021. TOTS 1B-Engine Room Operations-special circumst..

Search this section

Choose a question set and start learning or take an exam.

About this collection

The Seagull CBT bank is organised into modules covering safety, shipboard operations, maintenance and other topics. Original module names and codes are retained to help you find the topic you need.

“Seagull CBT — CD7021. TOTS 1B-Engine Room Operations-special circumst..” contains 33 questions across 1 collection.

Learning

Learning mode has no timer. After answering, you see feedback and the correct options. You can return to a question and repeat a topic.

Exam

A practice exam lasts up to 60 minutes and includes up to 50 questions from the selected collection. Correct answers and results appear after completion.

Sample questions and answers

These examples come from the published collection. Choose Learning to study questions in sequence, or Exam to check your knowledge.

On a slow speed main engine, the engine can be brought back into service after extinguishing a scavenge fire..

One correct answer

  • only after the cause of the fire is determined and the scavenge space cleaned out and inspected for damage.✓ Correct answer
  • as soon as the bridge confirms that the engine may be restarted.
  • only after the engine unit(s) in way of the fire have been fully overhauled.
  • once the engine has been turned over on the turning gear to ensure that it turns freely.
The safeguard against starting a slow speed direct drive engine with the fuel cam in the incorrect position is..

One correct answer

  • a wrong way alarm and interlock.✓ Correct answer
  • a wrong way alarm only.
  • a fuel cut off interlock only.
  • not fitted as it will automatically correct itself.
Unavailability of stand-by coolant supply pumps is..

One correct answer

  • significant and must be rectified as soon as possible.✓ Correct answer
  • significant and must be rectified before the engine is started.
  • not very significant and UMS operation of the engine room may be continued.
  • not very significant as one pump is enough for cooling.
On a vessel with 2 generators, while preparation is being made to depart on a 3 day voyage, one generator breaks down but cannot be repaired due to lack of a spare part. What should you do?

One correct answer

  • Cancel the departure and do not sail until the generator is back in service or a backup package generator is fitted.✓ Correct answer
  • Sail as planned and have the generator repaired in the next port as the voyage is very short.
  • Advise the office of the problem and agree to sail as the spare part will be arranged for the next port.
  • Sail as planned as the owner's representative is insisting that the vessel must not be delayed.
How is it ensured that important operations are carried out according to set procedures?

One correct answer

  • By using the appropriate critical operations check list.✓ Correct answer
  • By following the Chief Engineer's standing orders.
  • By using the manufacturer's operating / instruction manuals.
  • By using the Company operating manual.

Before you start

Do I need to register to start?

Guest access lasts 23 minutes. Free registration lets you continue without limits, save progress and review mistakes in your account.

What language are the questions in?

Questions and answer options retain the language of the original bank. You can change the interface language separately.